Current statusPlanning permit application lodged with the DTP in July 2026. Public notification underway.Application document on public notice: PA2604511Current statusPlanning permit application lodged with the DTP in July 2026. Public notification underway.Application document on public notice: PA2604511
Current statusPlanning permit application lodged with the DTP in July 2026. Public notification underway.Application document on public notice: PA2604511Current statusPlanning permit application lodged with the DTP in July 2026. Public notification underway.Application document on public notice: PA2604511
The Project

A single, integrated place of worship

What is being built, how it respects its setting, how it is being assessed, and where the application is up to.

What is proposed

At the heart of the site is the Mahā-Mandir, a traditional stone temple built in accordance with Hindu scripture. Around it, supporting buildings enable the full practice of the faith: prayer and ritual halls, religious education spaces, kitchens for sanctified vegetarian food (prasādam), visitor welcome and care facilities, and accommodation for the resident religious practitioners (sādhus). Together they function as one place of worship.

Built form that stays quiet in the landscape

The Mahā-Mandir is centrally located, with lower-scale supporting pavilions arranged in traditional Haveli courtyard forms. The central Shikhara towers are kept well away from public interfaces and key view corridors, softened by existing and new canopy planting. Buildings occupy only about 6% of the site, with total site coverage about 26%, and generous setbacks to every boundary.

Materials that weather into the setting

Natural, durable stone and masonry are proposed, with textured, non-reflective finishes and a restrained, subdued colour palette so the buildings integrate with the rural landscape. Detailed material selections are resolved at later design stages.

Why here

Melbourne is home to one of Australia’s fastest-growing Hindu communities, and the City of Casey is among the most culturally diverse municipalities in Victoria. Around 6.3% of Casey residents identify as Hindu, and more than 44,000 residents are of Indian ancestry, within a municipality experiencing strong population growth.

Despite this, there are few purpose-built Hindu places of worship able to support daily worship, major festivals and religious education at a regional scale. The Mahā-Mandir responds directly to that need, and it is designed to be open and inclusive, welcoming visitors of all faiths and backgrounds.

Source: Australian Bureau of Statistics, 2021 Census of Population and Housing (City of Casey), as cited in the project’s Social & Economic Benefit Report (Urbis, 2026).

Open to all

Hinduism is a non-proselytising faith. This place of worship is being built by the community, for the community: locals, visitors and school groups are all welcome. The site is also being designed for inclusion, with step-free access and accessible parking.

The project at a glance

Location
1390–1450 Western Port Highway, Cranbourne South
From the CBD
~45 km south-east of central Melbourne
Site area
42 hectares (420,672 m²)
Build period
Approximately 7 years
Hours
7:00am – 8:00pm daily
Key setbacks
~130 m to Western Port Highway; ~190 m to the eastern boundary; ~70–75 m to Homewood Road
Car parking
1,092 spaces (642 formal + 450 overflow), 49 drop-off / pick-up and 5 bus bays, all on site
Energy
All-electric, no gas connection, with rooftop solar

The journey so far

Seven steps from first site assessment to the Minister’s decision.

  1. 01
    2024 – early 2025

    Site assessment & concept design

    Specialist consultants were engaged to test the site and shape a masterplan that consolidates built form and protects the most sensitive land.

  2. 02
    March 2025

    Pre-application begins

    The Development Facilitation Program pre-application process opened with the Department of Transport and Planning.

  3. 03
    2025

    Consultation & referral

    Consultation with DTP, DEECA, council and First Nations; an EPBC referral was lodged federally.

  4. 04
    February 2026

    EPBC referral withdrawn

    The referral was withdrawn because the design retained all threatened-species habitat on the site.

  5. 05
    April – July 2026

    Technical assessments finalised

    The Eligibility Response and Project Snapshot were prepared alongside the full suite of specialist studies.

  6. 06
    July 2026

    Application lodged

    A formal planning permit application was lodged with DTP under the Development Facilitation Program (PPA-940).

  7. 07
    Underway

    Public notification

    The application is placed on public notification, so the community can make a formal submission through the DTP process ahead of the Minister’s decision.

    Where we are now